To the Residents of Dascomb Road and Adjacent Streets:
The Town of Andover, through its contractor Brox Industries, is preparing to proceed with repaving Dascomb Road from Andover Street to Steeple Court. This is a heavily trafficked stretch of road and we have considered alternatives that will minimize disruption to the neighborhood. On Wednesday, May 22nd and Thursday, May 23rd, the Town will proceed with night paving in order to mitigate impacts to the neighborhood. Overnight hours will be from 7 pm to 5 am. We acknowledge that it may cause disruption from both noise and lighting as crews proceed with this work. This approach is an alternative to an otherwise 3-day paving schedule that would have restricted residential access and resulted in significant traffic delays in your neighborhood.
For questions or concerns, please contact the Public Works Department at 978-623-8700. We appreciate your understanding as we move forward with this important project.
Christopher M. Cronin
Director of Public Works