Project Description: Proposed construction of a 5-story, 479,500 SF residential building comprised of 432 units, 2,950 SF retail space, and 144,000 SF open-air structured parking garage on property owned by JMC/SVP Old River Road LLC.
Upcoming Meetings:
- Tuesday, April 14, 2026 at 7:30PM in the School Committee Conference Room. Discussion topics: traffic, parking, offsite improvements, pedestrian connections, drainage and peer review follow-up.
Past Meetings:
- Tuesday, March 31, 2026. Due to technical difficulties in the Select Board Room, the public hearing was continued without discussion to the April 14, 2026 meeting.
- Tuesday, February 24, 2026 Presentation Recording Minutes
- Tuesday, March 10, 2026. Discussion topics included architecture, sustainability, landscaping, lighting, and retail strategy. Presentation Recording
Applicant Submittal
- Site Plan Review - Multifamily Overlay District River Road (MODRR) Application
- Special Permit for a Mixed-Use Structure Application
- Project Narrative
- Architectural Permit Set
- Civil and Landscape Permit Set
- Stormwater Management Report
- Transportation Impact Assessment Report
- Acentech Acoustical Report
- Retail Analysis & Proposed Programming Report
- Memorandum from the Health Department 2.5.26
- Memorandum from the Design Review Board 2.12.26
- Revised Architectural Permit Set 2.11.26
- Horsley Witten Group Initial Stormwater Peer Review 2.19.26
- Transportation Impact Assessment Supplement 2.27.26
- Supplemental Drainage Report 3.3.26
- Revised Civil and Landscape Permit Set 3.3.26
- Bohler Engineering Response to Stormwater Peer Review 3.4.26
- Goddard Consulting Response to Stormwater Peer Review & Invasive Species Management 3.4.26
- Horsley Witten Group Second Stormwater Peer Review 3.6.26
- Environmental Justice Screening Form 3.16.26
- Memorandum from the Department of Public Works 3.19.26
- APEX Traffic Peer Review #1 3.19.26
- Vanasse & Associates Response to Traffic Peer Review Comments 3.25.26
- Kimley Horn Technical Traffic Review on behalf of The Andover Companies 3.30.26
- Letter from MeVa 3.31.26
- River Road Amenities Map 3.31.26